First UAE unit begins commercial operation

April 6, 2021, 3:02PMNuclear News
Barakah-1 (right) is now providing reliable and sustainable electricity around the clock. Photo: ENEC

Unit 1 at the United Arab Emirates’ Barakah nuclear power plant has entered commercial operation and is now providing “constant, reliable, and sustainable electricity around the clock,” the Emirates Nuclear Energy Corporation (ENEC) announced this morning. ENEC added that, as a result of the event, the company now leads the largest decarbonization effort of any industry in the UAE.

Statement from UAE Section of ANS Chair Gale Hauck on Barakah

December 10, 2020, 10:59AMPress Releases

At Barakah Site, we feel so lucky to be a part of such a historic achievement and to have contributed in some small way. I came to the UAE almost three years ago with the hope that I could see a first core initial startup at least once in my career. Now that it’s happened, it’s a little surreal. While we celebrate our accomplishments at the site, we remain focused on our everyday work. There’s still much to do to ensure Units 2, 3, and 4 can safely start up on schedule.


Note: Hauck is also the Deputy Site Manager at Barakah for Westinghouse Electric Co.

First Barakah unit is connected to grid

August 20, 2020, 9:22AMNuclear News

Nawah Energy Company, in cooperation with the Abu Dhabi Transmission and Despatch Company (TRANSCO), has connected Unit 1 of the Barakah nuclear power plant to the United Arab Emirates’ power grid, according to an August 19 announcement from Nawah’s parent company, the Emirates Nuclear Energy Corporation (ENEC).

Barakah, located in the Al Dhafrah Region of Abu Dhabi, houses four 1,345-MWe APR-1400 pressurized water reactors. Unit 1 achieved first criticality earlier this month.

UAE’s Barakah-1 achieves first criticality

August 4, 2020, 12:34PMNuclear News

Initial criticality is achieved at Barakah-1. Photo: ENEC

Nawah Energy Company has successfully started up Unit 1 of the United Arab Emirates’ Barakah nuclear power plant, according to an announcement from Nawah’s parent company, Emirates Nuclear Energy Corporation (ENEC). One of four 1,345-MWe APR-1400 pressurized water reactors at the plant, Unit 1 achieved initial criticality on August 1.

ENEC completes key test for Barakah-4

May 22, 2020, 7:57AMNuclear News

The UAE's Barakah nuclear power plant in 2019. Photo: ENEC

Emirates Nuclear Energy Corporation (ENEC) has completed cold hydrostatic testing at Unit 4 of the Barakah nuclear power plant, the Arab world’s first such facility, located in Abu Dhabi. According to a May 19 ENEC press release, the testing incorporated lessons learned from the plant’s three other units and is a crucial step toward Unit 4’s completion. All four units are 1,345-MWe APR1400 pressurized water reactors. Abu Dhabi is the capital city of the United Arab Emirates.