Aalo Atomics’ final design review, attended by 40 DOE and NRC reviewers. (Photo: Aalo Atomics)
Two participants in the Department of Energy’s Reactor Pilot Program have recently announced significant milestones on their associated reactor projects. Aalo Atomics successfully completed its final design review (FDR), and Antares Nuclear has received DOE approval of its preliminary documented safety analysis (PDSA).
November 14, 2025, 12:10PMUpdated November 15, 2025, 12:30PMNuclear News Members of the Aalo team at the first ground-breaking ceremony for a project accelerated by the Reactor Pilot Program. (Photo: Aalo Atomics)
It has been about three months since the Department of Energy named 10 companies for its new Reactor Pilot Program, which maps out how the DOE would meet the goal announced in May by Executive Order 14301 of having three reactors achieve criticality by July 4, 2026.