WIPP begins placing TRU waste in Panel 8

December 2, 2022, 12:00PMRadwaste Solutions
Workers walk down a passageway in Panel 8 at the Waste Isolation Pilot Plant in November. (Photo: DOE)

Employees have begun emplacing defense-related transuranic (TRU) waste in Panel 8 of the Waste Isolation Pilot Plant (WIPP) in New Mexico, the Department of Energy’s Office of Environmental Management (EM) announced in November. TRU waste is permanently disposed of at WIPP in rooms mined in a Permian salt bed 2,150 feet below the surface.

Crews demolish first reactor in Oak Ridge’s central campus

November 15, 2022, 7:00AMRadwaste Solutions
Crews completed the teardown of Oak Ridge’s Bulk Shielding Reactor (Building 3010), once used for research as part of the federal Aircraft Nuclear Propulsion Program. (Photos: DOE)

The Department of Energy’s Office of Environmental Management (EM) said its cleanup contractor UCOR recently completed the first-ever demolition of a reactor in the central campus area at the Oak Ridge National Laboratory in Tennessee.

The Decommissioning of Portsmouth’s X-326

November 14, 2022, 3:00PMRadwaste SolutionsGuest Contributor

In the 1950s, the U.S. Department of Energy constructed the Portsmouth Gaseous Diffusion Plant in rural southern Ohio to enrich uranium, alongside two other federally owned and managed facilities in Oak Ridge, Tenn., and Paducah, Ky. The Cold War-era plant was built as a self-sufficient industrial city with more than 400 buildings and facilities centered around three massive gaseous diffusion process buildings that could enrich the level of the uranium-235 isotope for nuclear fuel in the defense and energy sectors.

Report links U-235 found in Ohio home to Portsmouth

November 8, 2022, 7:02AMRadwaste Solutions
A screenshot from the Local 12 report. (Image: WKRC/Sinclair)

In May 2019, Zahn’s Corner Middle School in Pike County, Ohio, located within four miles of the former Portsmouth Gaseous Diffusion Plant (PORTS), was closed after local officials reported enriched uranium and transuranic radionuclides were detected inside the school and at outside air monitors.

Now, Cincinnati’s WKRC Local 12, a news affiliate of Sinclair Broadcast Group, is reporting that a private house in Lucasville, Ohio, 10 miles from the PORTS site, has been contaminated with enriched uranium.

SRS workers meet Pu downblending goals ahead of schedule

November 7, 2022, 7:00AMRadwaste Solutions
A view of Savannah River’s K Area, where employees began downblending plutonium in 2016. (Photo: DOE)

Contractor employees at the Department of Energy’s Savannah River Site in South Carolina recently exceeded their plutonium downblending goal for 2022 ahead of schedule as part of the ongoing activities to remove Pu from the state, the DOE’s Office of Environmental Management (EM) announced.

DOE evaluates wearable robotic devices to aid cleanup workforce

November 4, 2022, 7:09AMRadwaste Solutions
Nicholas Spivey, left, an SRNL mechanical engineer, and Kurt Gerdes, director of EM’s Office of Technology Development, use virtual reality simulation of an EM worksite during meetings held at the IHMC in Pensacola, Fla. (Photo: DOE)

For the first time since forming in 2020, more than 40 members of a Department of Energy team met in person to evaluate technologies, including exoskeletons and wearable robotic devices, that could be adapted to the cleanup mission of department’s Office of Environmental Management (EM), helping improve the safety and well-being of its workers.

DOE completes cocooning of Hanford’s K East Reactor

October 31, 2022, 9:30AMRadwaste Solutions
DOE contractor CPCCo recently completed construction of a protective cocoon over the former K East Reactor building at Hanford. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) announced that construction of Hanford’s K East Reactor cocoon has been completed ahead of schedule and under budget. Cocooning of K East—enclosing it in a protective steel structure while the reactor’s radioactivity naturally decays—was one of EM’s key construction priorities for 2022.

“Abnormal condition” pauses Hanford melter heat-up

October 26, 2022, 3:25PMRadwaste Solutions
Workers install one of 18 startup heaters into Melter 1 of Hanford’s Low-Activity Waste Facility. (Photo: Bechtel National)

Heating of the first waste vitrification melter at the Department of Energy’s Hanford Site was paused after operators identified an “abnormal condition with the startup heater power supplies,” the DOE’s Office of River Protection (ORP) said. Heat-up of the 300-ton melter, which will be used to vitrify Hanford’s low-level radioactive tank waste, was initiated on October 8.

DOE awards $38 million to advance used fuel recycling

October 26, 2022, 6:38AMRadwaste Solutions

The Department of Energy is providing $38 million in funding for a dozen projects aimed at developing technologies to advance spent nuclear fuel reprocessing, reduce the volume of high-level waste requiring permanent disposal, and provide domestic advanced reactor fuel stocks. The projects are being led by universities, private companies, and national laboratories.

Oak Ridge’s Changing Skyline

October 21, 2022, 3:16PMRadwaste SolutionsCarol Hendrycks
An aerial photograph of Oak Ridge National Laboratory’s “Reactor Hill,” with, from left to right, reactor buildings 3042, 3005, and 3010. The DOE and its contractors are removing these excess contaminated facilities to eliminate risks and clear land for future research missions. (Photos: UCOR)

The Department of Energy and its environmental cleanup contractor United Cleanup Oak Ridge (UCOR) are poised to meet critical milestones as they continue to move to the next generation of cleanup at Oak Ridge National Laboratory in Tennessee. On ORNL’s main campus, crews on “Reactor Hill”—so named because of the four remaining reactor facilities on that hillside—and at the Experimental Gas-Cooled Reactor (EGCR) just east of the campus continue rigorous schedules as they enter a new phase of progress in the cleanup program.

NNSA to take over ownership of Savannah River from DOE-EM

October 21, 2022, 11:51AMRadwaste Solutions
A view of the Savannah River Site’s H Area. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) announced on October 18 that it has begun the process of transferring primary authority of South Carolina’s Savannah River Site (SRS) to the National Nuclear Security Administration, with the transfer expected to be completed in 2025.

DOE begins inspection of abandoned uranium mines in Navajo Nation

October 19, 2022, 7:00AMRadwaste Solutions
DRUM program members and others visit mine sites in the Navajo Nation during the spring of 2022. (Photo: DOE-LM)

The Department of Energy’ Office of Legacy Management (LM) will be conducting verification and validation work at abandoned uranium mines in the Navajo Nation of northeastern Arizona during the fall field season, which runs from mid-October to mid-December.

Heat-up of Hanford’s first vit melter begins

October 12, 2022, 12:01PMRadwaste Solutions
A screenshot from a 3D animation showing the heat-up of Hanford’s melters. (Image: DOE)

Crews at the Department of Energy’s Hanford Site, near Richland, Wash., have begun heating up the first of two 300-ton melters that will be used to vitrify mixed low-level radioactive and chemical tank waste. According to the DOE’s Office of Environmental Management (EM), initiating and completing the heating of the melter is a critical step to commissioning Hanford’s Waste Treatment and Immobilization Plant (WTP), which will treat and stabilize the site’s 56 million gallons of tank waste by immobilizing it in glass through the vitrification process.

DOE releases 5-year Hanford cleanup plan

October 11, 2022, 9:37AMRadwaste Solutions

By fiscal year 2027, Hanford’s Waste Treatment and Immobilization Plant (WTP) will ramp up toward producing 21 metric tons of low-level radioactive glass a day, according to the Department of Energy’s five-year plan for the site near Richland, Wash.

The plan, which was released on October 3 and opened for a 31-day public comment period, outlines what cleanup work will be initiated or completed at the Hanford Site during FYs 2023–2027.

Former criticality experiment lab demolished at Oak Ridge

October 6, 2022, 12:01PMRadwaste Solutions
Crews make progress tearing down the former Criticality Experiment Laboratory. The teardown began this past summer after months of deactivation activities. (Photo: DOE)

Work crews at the Department of Energy’s Oak Ridge Site in Tennessee have successfully completed the demolition of the former Criticality Experiment Laboratory. Crews worked this past summer to bring down the dilapidated 1940s-era facility, also known as Building 9213.

DOE extends Savannah River Site M&O contract

October 4, 2022, 7:01AMRadwaste Solutions
The Savannah River Site (Photo: DOE)

The Department of Energy has extended Savannah River Nuclear Solutions’ (SRNS) management and operating contract at the Savannah River Site (SRS) in South Carolina for up to an additional five years. The announcement was made recently 29 by engineering company Fluor, which leads the SRNS joint venture, along with Newport News Nuclear and Honeywell.

The DRUM program: Cataloging America’s abandoned uranium mines

September 30, 2022, 3:04PMRadwaste SolutionsGuest Contributor
DRUM team members at the Telluride 18 mine in the Yellow Cat area of southwest Colorado.

Based on a review of U.S. Atomic Energy Commission (AEC) records and available data from numerous agencies, there are an estimated 4,225 mines across the country that provided uranium ore to the U.S. government for defense-related purposes between 1947 and 1970. To aid in the cleanup of these legacy uranium mines and establish a record of their locations and current conditions, the Defense-Related Uranium Mines (DRUM) program was established within the Department of Energy’s Office of Legacy Management (LM).

Teardown commences on West Valley’s Main Plant

September 28, 2022, 12:00PMRadwaste Solutions
Demolition of the MPPB, one of the last remaining major facilities at WVDP, is expected to be completed in about 30 months. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) said it has met one of its cleanup priorities for 2022 by beginning demolition of the Main Plant Process Building (MPPB) at the West Valley Demonstration Project (WVDP) in New York. Located 35 miles south of Buffalo, the 150-acre WVDP site is home to the only commercial spent nuclear fuel reprocessing facility to operate in the United States.

DOE releases plan to guide cleanup mission, accelerate progress

September 27, 2022, 12:01PMRadwaste Solutions

The Department of Energy’s Office of Environmental Management (EM) released its EM Program Plan 2022, outlining a decision roadmap the cleanup program will use as a guide over the next two decades.

The new program plan, which was introduced by EM senior advisor William “Ike” White during the National Cleanup Workshop in Arlington, Va., on September 22, completes a trio of outward-facing planning documents, joining EM’s calendar year priorities list and its 10-year Strategic Vision.

DOE incentivizes interim storage with $16 million funding opportunity

September 26, 2022, 6:57AMRadwaste Solutions

The Department of Energy has announced that it will make $16 million in funding available to communities interested in learning more about “consent-based siting, management of spent nuclear fuel, and interim storage facility siting considerations.” The funding opportunity follows the DOE’s recent update to its consent-based process for siting an interim storage facility for SNF.