NRC issues Palisades’ final environmental assessment of no significant findings

May 30, 2025, 12:01PMNuclear News

The Palisades nulear power plant received a final “clean bill” of environmental assessment impact from the Nuclear Regulatory Commission today.

The findings of the NRC staff's EA showed no significant environmental impact for the Covert, Mich., plant, which plans to restart after operations were halted three years ago this month due to economic hardships in the energy market.

Researchers use one-of-a-kind expertise and capabilities to test fuels of tomorrow

May 26, 2025, 9:50AMNuclear NewsCory Hatch
Commercial nuclear fuel rods being unloaded from cask inside a HFEF hot cell. (Photo: INL)

At the Idaho National Laboratory Hot Fuel Examination Facility, containment box operator Jake Maupin moves a manipulator arm into position around a pencil-thin nuclear fuel rod. He is preparing for a procedure that he and his colleagues have practiced repeatedly in anticipation of this moment in the hot cell.

TVA files for Clinch River SMR construction permit

May 21, 2025, 7:01AMNuclear News
A rendering of the Clinch River SMR. (Image: TVA)

The Tennessee Valley Authority announced yesterday that it has submitted a construction permit application to the Nuclear Regulatory Commission for the construction of a GE Vernova Hitachi Nuclear Energy BWRX-300 small modular reactor at the Clinch River nuclear site in Oak Ridge, Tenn.

Urenco USA feeds UF6 into new U.S. commercial enrichment cascade

May 20, 2025, 12:00PMNuclear News
Urenco staff at the facility in Eunice, N.M. (Photo: Urenco)

Urenco USA has initiated production of enriched uranium in its newest gas centrifuge enrichment cascade—the first in a planned expansion of its Eunice, N.M., facility announced in July 2023. When the expansion is complete, early in 2027, the site will have increased its capacity by about 15 percent, adding about 700,000 separative work units (SWU) per year, the company said May 19.

“Robust” interest in Summer’s partially constructed reactors

May 19, 2025, 12:00PMNuclear News
The unfinished reactor containment building at Unit 2 of the V.C. Summer nuclear power plant in September 2024. (Photo: South Carolina's Nuclear Advisory Council)

Santee Cooper is satisfied with the response generated by its initial request for proposals to buy what remains of the Summer-2 and -3 nuclear power plant project in South Carolina. The RFP was issued in January and the application window closed May 5.

NRC discontinues spent fuel pool rulemaking

May 19, 2025, 7:00AMRadwaste Solutions

The Nuclear Regulatory Commission is discontinuing its rulemaking activity, “Long-Term and Unattended Water Makeup of Spent Fuel Pools,” and denying a petition for rulemaking. The new rule, as requested by the petitioner, would have required nuclear power plant licensees to ensure that their spent nuclear fuel pools are capable of cooling and maintaining water levels during extended power outages.

NRC news roundup

May 16, 2025, 9:30AMNuclear News
Unit 1 of the VC Summer nuclear power plant. (Photo: DJ Slaw)

Here’s a look at some recent announcements from the Nuclear Regulatory Commission.

Summer SLR: The NRC this month published its final environmental impact statement for Summer Unit 1’s subsequent license renewal application. Dubbed a supplemental EIS, the report is an important step in determining if Dominion Energy can continue operating its 966-MWe Westinghouse pressurized water reactor unit for an additional 20 years beyond August 6, 2042, the current end of its license.

EnergySolutions to seek early site permit for Kewaunee

May 14, 2025, 12:00PMNuclear News
The Kewaunee nuclear power plant in Wisconsin. (Photo: EnergySolutions)

Utah-based EnergySolutions announced that it is working with Milwaukee-based utilities company WEC Energy Group to explore new nuclear generation in Wisconsin and will begin efforts to pursue an early site permit from the Nuclear Regulatory Commission for the closed Kewaunee nuclear power plant in Wisconsin.

Xcel Energy reports on tritium levels in well near Mississippi River

May 14, 2025, 9:30AMNuclear News
The Monticello nuclear power plant in Minnesota. (Photo: Xcel Energy)

Recent testing of a monitoring well in Minnesota near the Mississippi River detected tritium levels just below the safety standards set by the Environmental Protection Agency, Xcel Energy reported this week.

TerraPower’s bid to start energy island construction gets EA/FONSI

May 12, 2025, 9:30AMNuclear News
An image of the energy island and the nuclear island of a Natrium reactor. (Image: TerraPower)

The Nuclear Regulatory Commission staff has concluded—with an assist from a Department of Energy environmental assessment released in February—that no environmental impact statement is needed for an exemption request from TerraPower that would allow the company to begin construction of the energy island of its planned Natrium sodium fast reactor in Kemmerer, Wyo. The NRC’s EA and finding of no significant impact (EA/FONSI), published on May 7, could clear the way for significant construction to begin while the NRC continues to review TerraPower’s construction permit application.

First concrete marks start of safety-related construction for Hermes test reactor

May 8, 2025, 3:01PMNuclear News
Drilling begins. (Photo: Kairos Power)

Kairos Power announced this morning that safety-related nuclear construction has begun at the Oak Ridge, Tenn., site where the company is building its Hermes low-power test reactor. Hermes, a scaled demonstration of Kairos Power’s fluoride salt–cooled, high-temperature reactor technology, became the first non–light water reactor to receive a construction permit from the Nuclear Regulatory Commission in December 2023. The company broke ground at the site in July 2024.

IAEA Director General meets with key nuclear leaders in D.C.

April 30, 2025, 12:43PMNuclear News
On his recent trip to Washington, D.C., IAEA director general Rafael Mariano Grossi (right) met with Energy Secretary Chris Wright. (Photo: IAEA/D. Candano)

International Atomic Energy Agency director general Rafael Mariano Grossi recently traveled to Washington, D.C., for the first time since Trump took office in January. In his three-day visit to the capital, Grossi spoke with key nuclear leaders from around the world and in the federal government, including Energy Secretary Chris Wright and Nuclear Regulatory Commission chair David Wright, on topics including nuclear power, safety, security, funding, and nonproliferation.

Industry Update—May 2025

April 29, 2025, 7:10AMNuclear News

Here is a recap of industry happenings from the recent past:

ADVANCED REACTOR MARKETPLACE

TerraPower’s Natrium reactor advances on several fronts

TerraPower has continued making aggressive progress in several areas for its under-construction Natrium Reactor Demonstration Project since the beginning of the year. Natrium is an advanced 345-MWe reactor that has liquid sodium as a coolant, improved fuel utilization, enhanced safety features, and an integrated energy storage system, allowing for a brief power output boost to 500-MWe if needed for grid resiliency. The company broke ground for its first Natrium plant in 2024 near a retiring coal plant in Kemmerer, Wyo.

UIUC microreactor fuel qualification methodology gets safety approval

April 24, 2025, 9:34AMNuclear News

The University of Illinois at Urbana-Champaign Nuclear Plasma and Radiation Engineering (NPRE) Department announced yesterday that the Nuclear Regulatory Commission has approved a fuel qualification methodology topical report for the high-temperature gas-cooled reactor the university wants to construct. The topical report was prepared by Ultra Safe Nuclear and submitted by UIUC to the NRC in March 2024. It describes the fuel that would be used in the microreactor that UIUC plans to host—initially containing uranium enriched to 9.9 percent U-235—and how it would be tested. The NRC issued its approval and a final safety evaluation on April 1.

Bill would require NRC reporting of nuclear medicine extravasations

April 22, 2025, 9:28AMNuclear News

Bipartisan legislation introduced into the U.S. House of Representatives earlier this month seeks to close a loophole that currently allows medical patients to be unintentionally exposed to radiation without reporting or disclosure. The Nuclear Medicine Clarification Act of 2025 (H.R. 2541) was introduced into the House by Reps. Don Davis (D., N.C.), Morgan Griffith (R., Va.), and Ben Cline (R., Va.), who said the legislation would improve care and ensure transparency for patients and simplify federal rules coming from the Nuclear Regulatory Commission.

TVA to file for Clinch River SMR construction permit by June

April 21, 2025, 3:45PMNuclear News
Deacy (left) speaks with senior project manager Mike McDowell (center) and civil construction manager Buck Collins (right) outside the construction trailer at the Clinch River site in Tennessee. (Photo: TVA)

In a Q&A posted on TVA’s website last week about a “new nuclear heyday,” Bob Deacy shared his vision for the Clinch River nuclear site in Oak Ridge, Tenn.—and some news about next steps for the company’s small modular reactor plans.

The Tennessee Valley Authority’s senior vice president for the Clinch River project, Deacy described his vision for up to four SMRs built on plots smaller than a football field with state-of-the-art digital equipment and a newly trained workforce providing reliable 24/7 power to the grid.

TerraPower begins U.K. regulatory approval process

April 18, 2025, 9:28AMNuclear News

Seattle-based TerraPower signaled its interest this week in building its Natrium small modular reactor in the United Kingdom, the company announced.

TerraPower sent a letter to the U.K.’s Department for Energy Security and Net Zero, formally establishing its intention to enter the U.K. generic design assessment (GDA) process. This is TerraPower’s first step in deployment of its Natrium technology—a 345-MW sodium fast reactor coupled with a molten salt energy storage unit—on the international stage.