Georgia Power again pushes back Vogtle project start dates

October 25, 2021, 9:29AMNuclear News
Vogtle-4 containment as it appeared last month. Photo: Georgia Power

In what has become for nuclear advocates an all-too-familiar refrain, Georgia Power has made another revision to the Vogtle nuclear expansion project schedule. The company now predicts a Unit 3 in-service date in the third quarter of 2022 and a Unit 4 in-service date in the second quarter of 2023, representing a three-month shift for each unit.

NRC may step up scrutiny of Vogtle project

August 31, 2021, 9:30AMNuclear News
Vogtle-3 (left) and -4 in June. (Photo: Georgia Power)

Oversight of the Vogtle nuclear new-build project will be increased if the preliminary conclusions in an August 26 Nuclear Regulatory Commission special inspection report are finalized.

Conducted from June 21 to July 2, the inspection looked into the cause and extent of construction-quality issues in the safety-related electrical cable raceway system at Vogtle-3.

Vogtle project suffers another setback

July 30, 2021, 12:00PMNuclear News
Vogtle Units 3 and 4, earlier this month. (Photo: Georgia Power)

Georgia Power yesterday announced that due to 'productivity challenges' and the need for 'additional time for testing and quality assurance,' it has revised the schedule for the Vogtle-3 and -4 nuclear expansion project. The new schedule pushes back the Unit 3 in-service date to the second quarter of 2022 and the Unit 4 date to the first quarter of 2023—a three-to-four-month shift for each unit.

Special inspection begins at Vogtle-3

June 23, 2021, 12:01PMNuclear News
Vogtle’s Unit 3, earlier this month. Photo: Georgia Power

The Nuclear Regulatory Commission has launched a special inspection at the Vogtle new-build site to identify the errors that necessitated construction remediation work on Unit 3’s electrical cable raceway system.

Experts predict further delay to commercial start of Vogtle-3

June 11, 2021, 7:02AMNuclear News
Vogtle-3’s containment (right) and turbine building (left) in May. Photo: Georgia Power

Georgia Power recently pushed back its projected commercial operation date for Vogtle-3 from December of this year to January 2022, but now some engineering and financial experts are saying that this revised date is too optimistic.

Vogtle project team reports delays, holds to approved start dates

October 28, 2020, 9:46AMNuclear News

In testimony filed last week with the Georgia Public Service Commission, Georgia Power and Southern Nuclear acknowledge that the “aggressive” target dates set in July for some of the Vogtle construction project’s upcoming milestones have had to be pushed back by a few months. At the same time, however, the companies continue to express confidence in being able to meet the regulatory-approved commercial start dates for the new reactors—November 2021 for Unit 3 and November 2022 for Unit 4.

The testimony was filed in support of Georgia Power’s Twenty-third Semi-annual Vogtle Construction Monitoring Report, released in August, which covers the period from January 1 to June 30, 2020.

Georgia Power provides Vogtle project update, addresses COVID concerns

September 3, 2020, 7:01AMAround the Web

Vogtle Unit 3, in August. Photo: Georgia Power

The target in-service dates for the Vogtle nuclear expansion project remain November 2021 for Unit 3 and November 2022 for Unit 4, plant owner Georgia Power announced in an August 31 report to the Georgia Public Service Commission. The project is now approximately 87 percent complete.