Vogtle project team reports delays, holds to approved start dates

October 28, 2020, 9:46AMNuclear News

In testimony filed last week with the Georgia Public Service Commission, Georgia Power and Southern Nuclear acknowledge that the “aggressive” target dates set in July for some of the Vogtle construction project’s upcoming milestones have had to be pushed back by a few months. At the same time, however, the companies continue to express confidence in being able to meet the regulatory-approved commercial start dates for the new reactors—November 2021 for Unit 3 and November 2022 for Unit 4.

The testimony was filed in support of Georgia Power’s Twenty-third Semi-annual Vogtle Construction Monitoring Report, released in August, which covers the period from January 1 to June 30, 2020.