Belarus’s first nuclear reactor connects to grid

The Belarusian nuclear power plant. Photo: Rosatom
Belarus on November 3 became the latest nation to begin generating electricity with nuclear energy when Unit 1 of the Belarusian nuclear plant was connected to the country’s power grid.
The Belarusian construction project, located in the Grodno region of Belarus, features twin 1,109-MWe pressurized water reactors, supplied by Rosatom, Russia’s state-owned nuclear energy corporation. The units are VVER-1200 Generation III+ designs, model AES 2006. Just last week, a VVER-1200 was connected to the Russian grid at the Leningrad plant.
The start-up program for Unit 1 began on August 7, when the first fuel assembly with fresh nuclear fuel was loaded into the reactor, according to a Rosatom press release. The reactor achieved first criticality on October 11.
Once fully completed, the plant is expected to supply approximately 18 billion kWh of low-carbon electricity to the Belarus national grid every year, Rosatom said.
-3 2x1.jpg)






The International Atomic Energy Agency has just released its latest projections for energy, electricity, and nuclear power trends over the next 30 years. Compared with the previous year, the new projections are largely unchanged.