Regulator releases report on Flamanville-3 pre-operational safety

August 14, 2020, 7:27AMNuclear News

The Flamanville nuclear plant. Photo: EDF

The French nuclear safety authority, Autorité de Sûreté Nucléaire (ASN), has released an International Atomic Energy Agency report on a pre-operational safety review team (pre-OSART) mission conducted in 2019 at the Flamanville nuclear plant to review the safety status of its Unit 3 EPR reactor, currently under construction.

According to the report, the pre-OSART mission at Flamanville-3 reviewed the following areas: leadership and management for safety, training and qualification, operations, maintenance, technical support, operating experience feedback, radiation protection, chemistry, emergency preparedness and response, accident management, human-technology-organization interaction, and commissioning. The review was performed by a team from Canada, Finland, Germany, Russia, Spain, Sweden, and the United States, along with IAEA staff members and observers from Russia and South Korea.

The results: The team identified 21 issues, resulting in 6 recommendations and 15 suggestions. Eight good practices were also identified. Several areas of good performance were noted, including “effective implementation of a holistic human factors approach throughout the life cycle of the plant,” according to the report.

Among the team’s proposals for improving operational safety were the following:

■ The plant should fully implement its Foreign Material Exclusion program throughout all departments and areas to attain a high standard level of implementation.

■ The plant should consider implementing procedures and practices to ensure that the potential impact of unsecured items on safety-related equipment in seismically qualified areas is minimized.

■ The plant should improve the arrangements and practices targeting the integrity of fire barriers and prompt fire suppression to ensure that fire risk is always minimized.

Flamanville-3 management has committed to addressing the issues identified and has invited a follow-up visit in about 18 months to review progress, the report said.

The 97-page document can be found here.

Background: Construction of Flamanville-3, a 1,600-MWe EPR supplied by Framatome, began in December 2007. The pouring of concrete for the reactor’s basemat commenced in December 2017, with hot functional testing completed in February 2020. In March, the French government published a decree postponing the deadline for fuel loading to April 2024.


Related Articles

Eisenhower’s “Atoms for Peace” at 70

December 8, 2023, 3:03PMNuclear News

Seventy years ago to the day, President Dwight D. Eisenhower gave his historic address to the United Nations General Assembly in New York City. (See December 2023 Nuclear News's “Leaders”...

Investments for peace

December 8, 2023, 7:01AMNuclear NewsKathryn Huff

President Dwight D. Eisenhower delivered his “Atoms for Peace” speech to the United Nations General Assembly in December 1953. In this historic address, he invoked the existential threat...

The WM Symposia’s 50th year

November 27, 2023, 9:30AMNuclear NewsGary Benda

This spring, Waste Management Symposia will celebrate its 50th anniversary when the conference convenes in Phoenix, Ariz., on March 10–14, 2024. Since the first international conference in...

The safe plan for Japan’s wastewater

November 7, 2023, 3:00PMNuclear News

There has been a lot of breathless coverage surrounding the release of mildly tritiated wastewater from the Fukushima Daiichi site, generated in no small part by people, organizations, and...

Nuclear’s fortunes looking up, says IAEA

October 11, 2023, 3:01PMNuclear News

The International Atomic Energy Agency has released the 2023 edition of its annual look at nuclear’s prospects in the coming decades—Energy, Electricity and Nuclear Power Estimates for the...