Diablo Canyon nuclear power plant in California. (Photo: PG&E)
The Nuclear Regulatory Commission has approved Pacific Gas & Electric’s application to extend the operating licenses for Diablo Canyon nuclear power plant’s two pressurized water reactors by another 20 years.
Thursday’s approval means Diablo Canyon-1 and -2 can now operate until November 2, 2044, and August 26, 2045, respectively, if California lawmakers agree. A 2022 state law requires the California Legislature to approve any extension of operations at Diablo Canyon that goes beyond 2030.
Three Mile Island nuclear power plant before its shutdown in 2019. (Photo: Constellation Energy)
When the former Three Mile Island-1 restarts in 2027 as the Crane Clean Energy Center, it will not face a delay of several years before it can be reconnected to the grid, Constellation CEO Joseph Dominguez said this week.
Among the items that emerged on Constellation and the Crane restart in Middletown, Pa., during last week’s CERAWeek energy conference was a Reuters report on an analysis from electric grid provider PJM suggesting the plant may not be connected to the grid until 2031.
Concept art showing the planned nuclear power plant at Lubiatowo-Kopalino. (Image: PEJ)
Polskie Elektrownie Jądrowe, Poland’s state-owned utility, has formally submitted an application for a construction license to build a nuclear power plant at the Lubiatowo-Kopalino site in Pomerania. The country’s first nuclear power plant will consist of three Westinghouse AP1000 units with a total installed capacity of 3,750 MWe. The construction and engineering contractor for the project is a U.S.-based consortium of Westinghouse and Bechtel.
More than 30 aircraft perform an “elephant walk” at Eielson Air Force Base in Alaska. (Photo: Eielson Air Force Base)
The U.S. Air Force wants to hear from companies that could be interested in deploying small nuclear reactors at its bases.
The request for information posted Wednesday intends to assist the federal government in identifying potential developers and “understanding the company’s capability to design, license, fuel, construct, and deploy Small, Micro, or Modular Reactor (SMR) technologies in compliance with applicable regulatory, safety, environmental, and security requirements.”
An image from a Microsoft video on the company’s “AI for nuclear” collaboration with Nvidia. (Image: Microsoft)
Microsoft and Nvidia have formed an “AI for nuclear” partnership intended to streamline the permitting, design, and operations of nuclear power plant facilities, and highlighted the collaboration at CERAWeek 2026 in Houston earlier this week.
Microsoft said in an announcement that the collaboration will build a “connected, AI-powered foundation” of AI tools that energy developers will be able to use to make work “repeatable, traceable, secure, and predictable,” all the while reducing work timelines and maintaining safety.
A cutaway of the BWRX-300 SMR design. (Image: GVH)
Coinciding with the March 19 White House meeting between President Trump and Japanese Prime Minister Takaichi Sanae, the Department of Commerce announced three new energy deals as part of a Japan-U.S. Strategic Investment initiative. Two of the deals involve the construction of natural gas generation facilities. The third, with an estimated value of as much as $40 billion, involves the construction of GE Vernova Hitachi (GVH) BWRX-300 small modular reactors in Tennessee and Alabama.
The campus map for Project Matador. (Source: Fermi America)
The Nuclear Regulatory Commission has released a notice of intent to conduct a scoping process and prepare an environmental impact statement to evaluate Fermi America’s plan to construct and operate four AP1000 reactors at its Project Matador Advanced Energy and Intelligence Campus in Texas.
While that announcement may seem routine, the process envisioned is not. As part of the company’s combined license (COL) application with the NRC, it has agreed to participate in an accelerated environmental review pilot program under the National Environmental Policy Act (NEPA). Under this pilot, the applicant(s) develop a draft EIS under NRC supervision.
The “chicken-and-egg” problem of the nuclear supply chain. (Graph: NSI)
A new report commissioned by the Nuclear Scaling Initiative, conducted by energy consultant Solestiss, and funded by the Bezos Earth Fund identifies and recommends solutions to overcome current bottlenecks in the supply chain for advanced reactors.
Broadly speaking, the report recommends the repeated deployment of Gen III+ reactor designs to rebuild the foundation of domestic manufacturing, workforce, and qualification capacity.
Palo Verde nuclear power plant in Arizona. (Photo: APS)
Arizona Public Service has informed the Nuclear Regulatory Commission of its intention to renew the operating licenses of the Palo Verde nuclear power plant’s three reactors for a second 20-year term, which could extend operations at the facility into the 2060s.
According to the announcement, APS won’t submit the subsequent license renewal application to the NRC until late 2027. The renewal would allow Unit 1 to operate through 2065, Unit 2 through 2066, and Unit 3 through 2067.
The Groves reactor module being lowered into place. (Photo: Oklo)
On March 17, Oklo released a series of four press releases in the span of a few hours containing some of the first substantial updates the company has given on its various approval processes with the Department of Energy and Nuclear Regulatory Commission since January.
Specifically, Oklo announced that it has received two nuclear safety design agreement (NSDA) approvals from the DOE and a materials license from the NRC.
The Palisades nuclear power plant in Covert Township, Mich. (Photo: Holtec)
At last week’s Regulatory Information Conference, Jamie Pelton cochaired a panel on Palisades nuclear power plant’s restart—a “historic restart,” as she put it.
Her choice of words was perhaps an understatement. After all, no U.S. nuclear plant has yet restarted after being slated for decommissioning.
Vogtle Unit 3, one of two Westinghouse AP1000 pressurized water reactors at the Georgia site. (Photo: American Nuclear Society/Dot Schneider)
March has put Westinghouse front and center in multiple news stories, from its role in Japan’s investment in U.S. nuclear energy to the economic impact that 10 potential AP1000 reactors could bring to the United States.
Waterford nuclear power plant in Louisiana. (Photo: Entergy)
The Nuclear Regulatory Commission has released its 2025 annual performance assessments of the country’s 95 operating commercial nuclear reactors. And of the 95 reactors, all but five earned the highest marks.
Nuclear power plant assessments can fall under one of five categories: Licensee Response, Regulatory Response, Degraded Cornerstone, Degraded Performance, and Unacceptable Performance. Ninety reactors fell under Licensee Response, the highest performance category in safety and security. Plants that achieve this level of performance are subject to a Reactor Oversight Process (ROP) baseline inspection.
U.S. Rep. Mike Lawler (R., N.Y.) speaks at the Indian Point site on March 6 as Energy Secretary Chris Wright listens. (Photo: Office of Congressman Mike Lawler)
Department of Energy Secretary Chris Wright joined U.S. Rep. Mike Lawler (R., N.Y.) at the site of the closed Indian Point nuclear power plant on Friday, March 6, as Lawler called for the reopening of the facility. He emphasized that the shutdown of the plant in 2021 has led to higher electricity costs for the people of New York state and increased strain on the state’s electric grid.