An aerial photo of Three Mile Island. (Photo: Constellation)
In a first quarter earnings call Monday, executives at Constellation said they should know in June or July the status of a request to the Federal Energy Regulatory Commission to transfer capacity interconnection rights from the company’s Eddystone gas- and-oil-powered plant in Pennsylvania to Crane nuclear power plant (formerly Three Mile Island-1).
Diablo Canyon nuclear power plant. (Photo: PG&E)
Originally scheduled for shutdown in 2025, Diablo Canyon nuclear power plant was given at least a few more years of life when in 2022, California lawmakers approved an extension of operations into 2030. The Avila Beach, Calif., plant already has the OK from the Nuclear Regulatory Commission to operate into 2044 and 2045 after the two reactors’ operating licenses were renewed and extended for another 20 years, but state lawmakers still must approve any further extension beyond 2030 if the plant is to remain in operation.
Bruce power plant in Ontario, Canada. (Photo: Bruce Power)
The Bruce C nuclear power plant expansion project in Ontario, Canada, moved one step closer to fruition last week with the May 7 announcement that Bruce Power and the provincial government of Ontario had entered into a cost-sharing and recovery agreement that could be worth C$300 million ($219.4 million).
Ontario has directed the province’s Independent Electricity System Operator (IESO) to enter into the agreement with Bruce Power so the Canadian utility can proceed with First Nations and community engagement, workforce planning, preconstruction and site preparation planning, and other critical activities that fall under predevelopment work. This work would be completed by 2030.
Cooling towers at the Hope Creek/Salem site. (Photo: Gov. Mikie Sherrill’s Office)
New Jersey’s two nuclear power plants, Hope Creek and Salem, may be joined by other nuclear facilities after lawmakers lifted the state’s de facto moratorium on new nuclear construction.
Gov. Mikie Sherrill said state officials are eyeing sites for potential nuclear facilities. Executives at PSEG Nuclear—the operators of Hope Creek and Salem—welcome the news of the growing momentum for nuclear power in the state but cautioned it will take more than lifting a moratorium to make this feasible.
Artist’s concept of Radiant’s R-50 facility in Oak Ridge, Tenn. (Image: Radiant)
The Nuclear Regulatory Commission has accepted Radiant Industries’ 10 CFR Part 70 license application for its R-50 microreactor production facility in Oak Ridge, Tenn., and will launch an expedited review that it is aiming to complete within eight months.
According to NRC documents, the agency expects to complete its review of the license application by December 18, 2026. The timeline is described as “accelerated” in the NRC announcement—about 55 percent faster than the typical 18 months for Part 70 application reviews.
St. Lucie nuclear power plant. (Photo: FPL)
The Nuclear Regulatory Commission has approved subsequent license renewals for St. Lucie Units 1 and 2, extending the operating licenses for the pressurized water reactors by another 20 years.
Tuesday’s approval means that the 1,062-MWe Unit 1 and 1,074-MWe Unit 2 can now operate until March 1, 2056, and April 6, 2063, respectively. Unit 1 commenced operations in 1976 and Unit 2 in 1983. With the original 40-year operating licenses and first 20-year renewals, these second 20-year renewals bring the reactors’ lifespan to 80 years.
Robinson nuclear power plant in Hartsville, S.C. (Photo: Duke Energy)
The Nuclear Regulatory Commission has renewed the Robinson nuclear power plant’s operating license in record time, the agency announced last week.
The subsequent license renewal process for the Hartsville, S.C., facility was completed within 12 months, according to the NRC. The process has typically taken 18 months. This was the first license renewal review conducted under the directive of Executive Order 14300 to streamline processes like renewing operating licenses.
Duane Arnold nuclear power plant. (Photo: NextEra Energy)
The communities in and around Duane Arnold had a chance on Tuesday evening to hear from Nuclear Regulatory Commission officials on the progress to restart Iowa’s only nuclear power plant in early 2029.
Licensing, inspections and assessments, the noticing process, and the role of the restart panel were among the topics discussed at the public meeting, which was held in Cedar Rapids, Ia., with an option for virtual attendance.
Diablo Canyon nuclear power plant in California. (Photo: PG&E)
The Nuclear Regulatory Commission has approved Pacific Gas & Electric’s application to extend the operating licenses for Diablo Canyon nuclear power plant’s two pressurized water reactors by another 20 years.
Thursday’s approval means Diablo Canyon-1 and -2 can now operate until November 2, 2044, and August 26, 2045, respectively, if California lawmakers agree. A 2022 state law requires the California Legislature to approve any extension of operations at Diablo Canyon that goes beyond 2030.
Three Mile Island nuclear power plant before its shutdown in 2019. (Photo: Constellation Energy)
When the former Three Mile Island-1 restarts in 2027 as the Crane Clean Energy Center, it will not face a delay of several years before it can be reconnected to the grid, Constellation CEO Joseph Dominguez said this week.
Among the items that emerged on Constellation and the Crane restart in Middletown, Pa., during last week’s CERAWeek energy conference was a Reuters report on an analysis from electric grid provider PJM suggesting the plant may not be connected to the grid until 2031.
Concept art showing the planned nuclear power plant at Lubiatowo-Kopalino. (Image: PEJ)
Polskie Elektrownie Jądrowe, Poland’s state-owned utility, has formally submitted an application for a construction license to build a nuclear power plant at the Lubiatowo-Kopalino site in Pomerania. The country’s first nuclear power plant will consist of three Westinghouse AP1000 units with a total installed capacity of 3,750 MWe. The construction and engineering contractor for the project is a U.S.-based consortium of Westinghouse and Bechtel.