The chemical vapor infiltration furnace at BWXT’s Lynchburg Technology Center in Lynchburg, Va. (Photo: BWXT)
BWX Technologies (BWXT) has achieved a key milestone in its project to additively manufacture advanced forms of TRISO fuel for Generation IV advanced nuclear reactors. The Lynchburg Technology Center of subsidiary company BWXT Advanced Technologies, located in Lynchburg, Va., has successfully installed and tested a chemical vapor infiltration (CVI) furnace that solidifies pre-forms that are then filled with TRISO particles, a fuel consisting of carbon and silicon layers surrounding a uranium kernel.
Concept art of TerraPower’s Natrium plan. (Image: TerraPower)
The Nuclear Regulatory Commission has whittled down the timeline for reviewing TerraPower’s construction permit application for Kemmerer Power Station Unit 1 in Wyoming. Announcing a new, more aggressive schedule, the NRC said it aims to complete its review by the end of 2025, eight months earlier than originally planned.
Drilling begins. (Photo: Kairos Power)
Kairos Power announced this morning that safety-related nuclear construction has begun at the Oak Ridge, Tenn., site where the company is building its Hermes low-power test reactor. Hermes, a scaled demonstration of Kairos Power’s fluoride salt–cooled, high-temperature reactor technology, became the first non–light water reactor to receive a construction permit from the Nuclear Regulatory Commission in December 2023. The company broke ground at the site in July 2024.
Xe-100 Dow Seadrift concept art. (Image: X-energy)
Dow and X-energy announced today that they have submitted a construction permit application to the Nuclear Regulatory Commission for a proposed advanced nuclear project in Seadrift, Texas. The project could begin construction later this decade, but only if Dow confirms “the ability to deliver the project while achieving its financial return targets.”
Workers begin construction at the Hermes site in Oak Ridge, Tenn. (Photo: Kairos Power)
Earlier today, on a site in Oak Ridge, Tenn., that was formerly home to the K-33 Gaseous Diffusion Plant, Kairos Power marked the start of construction on its low-power demonstration reactor. Named Hermes, the 35-MWt test reactor claims status as the first Gen IV reactor to be approved for construction by the Nuclear Regulatory Commission and the first non–light water reactor to be permitted in the United States in more than 50 years.
Concept art of the planned X-energy helium test facility. (Image: DOE OCED)
The Department of Energy’s Office of Clean Energy Demonstrations issued a final environmental assessment (EA) and finding of no significant impact in February for a cost-shared X-energy project to construct and operate a helium test facility (HTF) in Oak Ridge, Tenn. According to the EA, construction would begin in early 2024 and take X-energy and its contracted partner, Kinectrics, about one year to complete. the facility would then operate for six years, with the possibility of extensions for up to an additional 20 years, to test equipment for a demonstration of X-energy’s high-temperature, gas-cooled reactor technology and also to “serve the reactor community at large as the technology continues to develop and is adopted around the world.”
Image from the DOE’s draft EA showing a rendering of the TFF building. (Image: DOE)
The Department of Energy’s Office of Clean Energy Demonstrations issued a draft environmental assessment (EA) in early November for a test and fill facility (TFF) that TerraPower plans to build in Kemmerer, Wyo.—the town selected two years ago to host the company’s first Natrium sodium fast reactor. The draft EA, open for comment through December 1, describes TerraPower’s plans to construct a nonnuclear facility that would safely store about 400,000 gallons of sodium to test coolant system designs and ultimately fill the planned reactor.