First RPV for Turkish nuclear plant arrives

November 18, 2020, 6:59AMNuclear News

The Unit 1 reactor pressure vessel arrives at the Akkuyu site. Photo: Akkuyu Nuclear JSC

Russian company Atommash has delivered the reactor pressure vessel for Unit 1 of the Akkuyu plant, the nuclear power facility under construction in Turkey, Akkuyu Nuclear JSC announced recently.

Atommash is a branch of AEM Technologies, which is part of Atomenergomash, the equipment-building division of Rosatom, Russia’s state atomic energy corporation. Akkuyu Nuclear, based in Ankara, was established to implement the Russian-Turkish project.

It took some three years to manufacture the 330-metric ton, 12-meter-long reactor pressure vessel and 20 days to transport it from the Atommash plant in Volgodonsk, Russia, to the eastern cargo terminal at the Akkuyu plant site, according to Akkuyu Nuclear.

Background: The Russian and Turkish governments signed a cooperation agreement in May 2010 for the construction of the Akkuyu plant. The project involves the construction of four 1,114-MWe Generation III+ VVER pressurized water reactors, model AES-2006. The design is based on the new generation of reactors being built in Russia, the first of which was Novovoronezh II-1. Akkuyu-1 is scheduled for commercial operation in 2023, with Units 2, 3, and 4 to follow in 2024, 2025, and 2026, respectively.

When all four Akkuyu reactors are in operation, they will generate an estimated 10 percent of Turkey’s electricity, according to Rosatom. The $20-billion project is the world’s first nuclear power plant to be built using the build-own-operate financing model.