ANS is committed to advancing, fostering, and promoting the development and application of nuclear sciences and technologies to benefit society.
Explore the many uses for nuclear science and its impact on energy, the environment, healthcare, food, and more.
Explore membership for yourself or for your organization.
Conference Spotlight
2026 Nuclear Energy Conference & Expo (NECX)
August 24–27, 2026
Dallas, TX|Hilton Anatole
Latest Magazine Issues
Aug 2026
Jan 2026
2026
Latest Journal Issues
Nuclear Science and Engineering
September 2026
Nuclear Technology
Fusion Science and Technology
August 2026
Latest News
NRC issues draft EA/FONSI for Duane Arnold restart
Efforts by NextEra Energy to restart the Duane Arnold nuclear power plant as early as 2029 continue to move forward with the Nuclear Regulatory Commission's preliminary environmental assessment and determination that the restart would have no significant environmental impacts.
On Thursday, the NRC posted a draft environmental assessment and a finding of no significant impact for the Palo, Iowa, facility; the Federal Register notice was published on Monday. The Department of Energy’s Office of Energy Dominance Financing is a cooperating agency on the draft EA, as the DOE is considering providing financial assistance to the restart project.
Peter H. Titus, L. Dudek, M. Smith, A. Brooks
Fusion Science and Technology | Volume 68 | Number 2 | September 2015 | Pages 416-422
Technical Paper | Proceedings of TOFE-2014 | doi.org/10.13182/FST14-993
Articles are hosted by Taylor and Francis Online.
The National Spherical Torus Experiment Upgrade (NSTX-U) is currently under construction at Princeton Plasma Physics Laboratory (PPPL) It is scheduled to start operations early in 2015. Upgrade designs were analyzed and qualified prior to the beginning of construction, but many issues arose during manufacture and assembly that required adjustments in design and analysis of components. Some designs relied on testing that occurred after final design when the actual material and processes were selected by vendors or in-house shops. Design of some components, like the bus bars, was deferred until field run interferences could be identified. Some components used materials that did not meet original specifications. New materials or processes had to be found and components sometimes needed requalification. PPPL responsible or “Cognizant Engineers” (COG’s) and analysts worked closely to work out resolution of issues and perform redesign and reanalysis. Revisions to calculations were prepared and filed. Some significant items addressed during the construction period (or Title III in DOE parlance) are selected for more detailed discussion.