Darlington unit overhaul ahead of schedule

August 23, 2022, 3:00PMNuclear News
The Darlington-3 reactor face. (Photo: OPG)

Ontario Power Generation has announced that refurbishment of Unit 3 at its Darlington nuclear plant is progressing ahead of schedule, with an expected return to service by late 2023, rather than early 2024.

Darlington-1 begins refurbishment

February 18, 2022, 12:00PMNuclear News
An aerial view of Ontario’s Darlington Nuclear Generating Station. (Photo: OPG)

Ontario Power Generation has passed the midway point in its C$12.8 billion (about $10 billion) Darlington nuclear plant refurbishment project with the start of work on Unit 1, the company has announced. The unit is expected to be ready for grid reconnection in the second quarter of 2025.

Darlington houses four 878-MWe CANDU pressurized heavy water reactors, all of which entered commercial operation in the early 1990s. The plant is located in Clarington, Ontario, Canada.