Vogtle-3 back on line following unplanned outage

July 17, 2024, 11:18AMUpdated July 17, 2024, 8:24PMNuclear News
Unit 3 at the Vogtle nuclear power plant. (Photo: Georgia Power)

One of the new Vogtle units in Georgia was shut down unexpectedly on Monday last week for a valve issue that has since been investigated and repaired. According to multiple local news outlets, Georgia Power reported on July 17 that Unit 3 was back in service.

Southern Company spokesperson Jacob Hawkins confirmed that Vogtle-3 went off line at 9:25 p.m. local time on July 8 “due to lowering water levels in the steam generators caused by a valve issue on one of the three main feedwater pumps.”

To continue reading, log in or create a free account!

Related Articles

From quad to grid: Where thought leadership sparks civic dialogue

The role of state universities as trusted anchors for public engagement in an age of energy and environmental transition

August 27, 2025, 7:05AMNuclear NewsSukesh Aghara

In an era when affordable, clean energy is as much an economic imperative as it is an environmental one, the Commonwealth of Massachusetts has an opportunity to lead not just through...

Westinghouse awarded $180M ITER contract

July 3, 2025, 9:30AMNuclear News

Westinghouse Electric Company announced that it has signed a $180 million contract with the ITER Organization for the assembly of the vacuum vessel for the fusion reactor being built in...