Final major module for Vogtle-3 installedNuclear NewsPower & OperationsMay 27, 2020, 5:18PM|Nuclear News StaffThe CB-20 module being installed at Vogtle-3. Photo: Georgia PowerA massive water tank has been placed atop the containment vessel and shield building roof at Vogtle-3, one of two AP1000 reactors currently under construction at Southern Company’s nuclear expansion project near Waynesboro, Ga. The installation represents the final module placement for the unit and marks the latest significant milestone to be reached at the Vogtle site.Module specs: The water tank, known as CB-20, is a major part of the AP1000’s advanced passive safety system, according to the Vogtle plant’s primary owner, Southern subsidiary Georgia Power. Standing 35 feet tall and weighing more than 720,000 pounds, the CB-20 module will hold approximately 750,000 gallons of water, which would flow down in the event of an emergency to help cool the reactor. The water can also be directed into the used fuel pool, while the tank itself can be refilled from water stored elsewhere on-site, Georgia Power said.Tags:ap1000georgia powersouthern companyvogtleShare:LinkedInTwitterFacebook
More adjustments to Vogtle milestone dates likelyThe initial shipment of nuclear fuel for Unit 3 arrives at the Vogtle site in December. Photo: Georgia PowerLargely as a result of the continuing COVID-19 crisis, the Vogtle reactor-construction project team expects to further adjust dates for achieving key project milestones, including the start of hot functional testing and fuel load for Unit 3, Southern Company subsidiary Georgia Power announced on January 11.The company added, however, that it continues to expect to bring Unit 3 into service this November and Unit 4 into service in November 2022. Additional updates on the project will be provided during Southern’s quarterly earnings call next month.Go to Article
Delay, cost increase announced for U.K. nuclear projectPerspex screens and reduced seating capacity in the Hinkley Point canteens help protect the workforce during breaks, EDF Energy said. Photo: EDF EnergyThe unfortunate effects of the COVID-19 pandemic on nuclear new-build projects haven’t stopped with Vogtle: EDF Energy this morning reported that the expected startup date for Unit 1 at its Hinkley Point C site is being pushed from late 2025 to June 2026.In addition, the project’s completion costs are now estimated to be in the range of £22 billion to £23 billion (about $30.2 billion to $31.5 billion), some £500 million (about $686 million) more than the 2019 estimate, EDF said, adding the caveat that these revisions assume an ability to begin a return to normal site conditions by the second quarter of 2021.Go to Article
DOE lists five stories to watch in 2021Despite all the challenges of the COVID-19 pandemic, the U.S. nuclear energy community pulled out some big wins in 2020, and this year could be even bigger, according to the Department of Energy’s Office of Nuclear Energy.From deep space exploration on Mars to a historic new reactor coming online in Waynesboro, Ga., 2021 will be a record-breaking year for the industry—both good and potentially bad.Find the full details on the DOE-NE website.Go to Article
Hitachi sunsets HorizonHitachi Ltd. plans to close Horizon Nuclear Power, its U.K. nuclear development subsidiary, early this spring, according to weekend news reports. Horizon is the firm behind Wylfa Newydd, the proposed nuclear new-build project in Wales.On January 10, citing a story that appeared earlier that day in The Times, Yahoo reported that Hitachi will close Horizon by March 31—a move, Yahoo said, that “could scupper a sale of the [Wylfa Newydd] site, which has attracted interest from bidders, including a U.S. consortium of Bechtel, Southern Company, and Westinghouse, and dent [the] U.K.’s clean energy goals.”However, a January 11 item on a Welsh online news service stated, “It is understood that if a sale of the site is not secured before Horizon shuts, the sale process will be continued by Hitachi.”Go to Article
When adverse action meets protected activity: Protecting employees and employers while upholding safety cultureWorkers in nuclear must be free to report potential problems without fear of retaliation. When it comes to issuing adverse actions, employers have a responsibility to ensure that protected activity rights are not infringed.Go to Article
First fuel shipment for Vogtle-3 deliveredSouthern Company subsidiary Georgia Power has announced the receipt of the initial shipment of nuclear fuel for Vogtle-3, characterizing the event as a “major step” for the two-unit nuclear expansion project currently under way at the Vogtle nuclear power plant near Waynesboro, Ga.Next step: With the receipt of the first nuclear fuel assemblies, the project is now focused on one of the major milestones for Unit 3, hot functional testing, the last critical step before fuel load and, ultimately, in-service operation, Georgia Power said.In October, Vogtle plant operator Southern Nuclear announced a readjustment of its July 2020 “aggressive site schedule” dates for Unit 3 hot functional testing, fuel load, and commercial operation. The dates were moved from October 2020, December 2020, and May 2021, respectively, to January 2021, April 2021, and the third quarter of 2021. Southern Nuclear said that hot functional testing could start as late as the end of March 2021 and fuel load as late as mid-year 2021 without jeopardizing Vogtle-3’s November 2021 regulatory approved in-service date.Go to Article
Five advanced reactor designs get DOE risk reduction fundingThe Department of Energy today announced $30 million in initial fiscal year 2020 funding—with the expectation of more over the next seven years—for five companies selected for risk reduction for future demonstration projects. The chosen reactor designs from Kairos Power, Westinghouse, BWX Technologies, Holtec, and Southern Company collectively represent a range of coolants, fuel forms, and sizes—from tiny microreactors to a molten salt reactor topping 1,000 MWe. They were selected for cost-shared partnerships under the Office of Nuclear Energy’s Advanced Reactor Demonstration Program (ARDP) through a funding opportunity announcement issued in May 2020.“All of these projects will put the U.S. on an accelerated timeline to domestically and globally deploy advanced nuclear reactors that will enhance safety and be affordable to construct and operate,” said Energy Secretary Dan Brouillette. “Taking leadership in advanced technology is so important to the country’s future, because nuclear energy plays such a key role in our clean energy strategy.”Go to Article
U.S. companies said to be in talks with U.K. on Welsh nuclear projectArtist's concept of the Wylfa Newydd project. Image: Horizon Nuclear PowerThe London-based newspaper Financial Times is reporting that a consortium of U.S. firms is holding discussions with the U.K. government to revive Wylfa Newydd, the nuclear new-build project in Wales from which Tokyo-based Hitachi Ltd. withdrew in September. According to the November 10 FT story—which is based on an anonymous source—the consortium is led by Bechtel and includes Southern Company and Westinghouse.Go to Article
Core Power thinks nuclear will make waves in commercial shippingIllustration of Core Power’s modular MSR concept. Image: Core PowerCore Power is a tiny startup that is bullish on the prospects for nuclear-powered ocean transportation. The company announced on November 2 that it is part of a team that has applied for a cost-shared award from the Department of Energy’s Advanced Reactor Demonstration Program (ARDP) to build a prototype molten salt reactor (MSR). Core Power believes that MSRs could be used for propulsion or electricity generation to decarbonize the world’s commercial shipping fleet.Based in London, England, Core Power is the only non-U.S. member of the team, which includes TerraPower, Southern Company, and Orano USA. As a marine engineering firm, Core Power says that it offers its ARDP partners “access to pent-up demand from a market with real customers.” An announcement of ARDP “risk reduction for future demonstrations” award winners is expected in December.Go to Article
Vogtle project team reports delays, holds to approved start datesIn testimony filed last week with the Georgia Public Service Commission, Georgia Power and Southern Nuclear acknowledge that the “aggressive” target dates set in July for some of the Vogtle construction project’s upcoming milestones have had to be pushed back by a few months. At the same time, however, the companies continue to express confidence in being able to meet the regulatory-approved commercial start dates for the new reactors—November 2021 for Unit 3 and November 2022 for Unit 4.The testimony was filed in support of Georgia Power’s Twenty-third Semi-annual Vogtle Construction Monitoring Report, released in August, which covers the period from January 1 to June 30, 2020.Go to Article