NRC spots significant safety issue at Summer plant

October 13, 2023, 12:00PMNuclear News
Dominion Energy's V. C. Summer plant near Jenkinsville, S.C. (Photo: NRC)

The Nuclear Regulatory Commission last week issued a preliminary “yellow” finding to Dominion Energy for failing to resolve a two-decade-long problem with cracks in the piping of the V. C. Summer plant’s emergency diesel generator (EDG) fuel oil system.

Former SCANA CEO pleads guilty to fraud

March 1, 2021, 9:30AMNuclear News

The latest episode in the continuing saga of the failed nuclear expansion project at South Carolina’s Summer plant played out in federal court last week when the former chief executive officer of SCANA, Kevin Marsh, pleaded guilty to charges of fraud. According to the state attorney general’s office, Marsh will serve two years of a 10-year sentence, followed by three years of probation, provided he continues to cooperate with prosecutors. Marsh will also part with $5 million, which is to be used to help low-income ratepayers with their utility bills.

“This case is a good example of the power of our state grand jury and how our office uses it to hold the powerful accountable,” said South Carolina attorney general Alan Wilson. “While this criminal proceeding is not meant to repay the customers who spent billions of dollars on nuclear plants that were never finished, we hope they take some comfort from the fact that the former CEO of SCANA has pled guilty for his role in this debacle. A public utility and its officers must serve the public.”