“There’s going to be a cliff”: Preparing an international SMR supply chain

November 3, 2022, 12:32PMNuclear News
Participating in the forum were (from left) John Hopkins (NuScale Power), Renaud Crassous (EDF), Daniel Poneman (Centrus Energy), Adriana Cristina Serquis (CNEA), and Boris Schucht (Urenco).

The nuclear industry leaders assembled in Washington, D.C., last week to discuss small modular reactor supply chains agreed that lost generation capacity from the expected retirement of hundreds or thousands of coal power plants over the next decade—a cliff, in one panelist’s words—represents an opportunity that developers of SMRs and advanced reactors are competing to meet.

“I think in total 80 projects are ongoing,” said Boris Schucht, panel moderator and chief executive officer of Urenco Group, as he opened the forum. “Of course not all of them will win, and we will discuss today what is needed so that they can be successful.”

Advanced reactor licensing and the path to cost certainty

September 20, 2022, 3:13PMNuclear NewsMike Laufer

Laufer

Developing a first-­of-­a-­kind reactor is a daunting endeavor. To be successful, advanced reactor designers need to achieve cost certainty by delivering a safe and affordable product at the promised cost. To meet this goal, Kairos Power structured its approach around four key strategies: 1) achieving technology certainty through a rapid iterative approach; 2) achieving construction certainty by demonstrating the ability to build it; 3) achieving licensing certainty by proving Kairos can license it; and 4) achieving supply chain certainty by vertically integrating critical capabilities. By mitigating risk in these four key areas, Kairos Power is confident that it will get true cost certainty for our future products.

The third prong in Kairos’s strategy—achieving licensing certainty—was a key driver in the decision to build the Hermes low-­power demonstration reactor, and it remains a major workstream as the company’s construction permit application (CPA) undergoes review by the U.S. Nuclear Regulatory Commission. Licensing a new nuclear technology is no small challenge, and there are multiple approaches companies can take. Here’s a look at how we at Kairos are approaching it.

Collaboration and teamwork are crucial to solving nuclear supply chain challenges

August 26, 2022, 2:59PMNuclear NewsGeorge Shampy

George Shampy

Across the country, supply chain issues continue making the news: price escalation, inflation, logistical delays, scarcity of products and services, obsolescence, risk associated with just-­in-­time inventory, equipment and service quality, and—especially in nuclear—the financial pressures to reduce costs while maintaining our focus on safe, secure, and reliable plant operations.

Unfortunately, these are not new challenges for nuclear supply chain professionals.

In fact, in 2001, the Nuclear Energy Institute formed the Nuclear Supply Chain Strategic Leaders Group (NSCSL) in conjunction with the Institute of Nuclear Power Operations (INPO) and Electric Power Research Institute (EPRI) after an American Nuclear Society Utility Working Conference networking event. The NSCSL is composed of utility supply chain managers and directors and serves as the “community of practice” for these subject matter experts. I am privileged to be an NSCSL participant and an Entergy team member. The NSCSL was designed to be the industry go-­to group for materials and service collaborations and needed supply chain solutions.

NuScale and U.S. Reactor Forging Consortium to collaborate on SMR deployment

May 3, 2022, 9:30AMNuclear News

NuScale Power has signed a collaboration agreement with the U.S. Reactor Forging Consortium (RFC) to leverage the nation’s forging supply chain to prepare for the deployment of NuScale’s small modular reactor technology and to support, maintain, and expand U.S. manufacturing jobs.

Radiological waste transportation & disposal: A decommissioning manager’s perspective

April 1, 2022, 12:00PMRadwaste SolutionsAndy Lombardo
Waste packages are loaded with contaminated soil during remediation work at Lawrence Berkeley National Laboratory. (Photo: PermaFix)

Depending on the size and complexity of a decommissioning project, the transportation and disposal of radioactive waste will have an oversized impact on planning, schedule, and budget. The scope of decommissioning a site contaminated with radioactive material begins and ends with the proper and safe packaging of waste and subsequent transportation from the site to the final disposal location. Once all of the waste is gone from the site, the compliance exercise can be completed and the site released from controls (i.e., the radioactive materials license is terminated and the site is decommissioned).

Predictions: What lies ahead for nuclear in 2022

January 21, 2022, 3:26PMNuclear News

As we begin a new year, it is natural not only to look back (see page 24 for top news stories of 2021) but also to look forward. Nuclear News reached out to leaders in the nuclear community to get their predictions on what 2022 has in store, whether broadly or for their specific areas within the community. Although the responses below are wide-ranging and varied, one thing is made clear by all of the respondents: 2022 will see growth and opportunity. The future for nuclear is bright.

The U.S. nuclear supply chain: Time to start the climb

August 12, 2020, 4:30PMANS NewsCraig Piercy

Craig Piercy

Originally published in the August 2020 issue of Nuclear News.

Dear reader:

Let’s face it. The U.S. nuclear manufacturing and supply chain is not what it once was. In the 1960s and ’70s, America was the dominant player in the global nuclear industry. Under the auspices of Atoms for Peace, U.S. companies successfully provided reactor systems and associated services to countries across the world and held significant sway over the course of future nuclear development in the international arena. America was at the top of its nuclear game.