North Anna license renewal arguments to be aired

January 29, 2021, 7:00AMNuclear News

An aerial view of the North Anna nuclear plant. Photo: Dominion Energy

A Nuclear Regulatory Commission Atomic Safety and Licensing Board will conduct an “oral argument” via WebEx early next month regarding a petition to hold a hearing on North Anna’s subsequent license renewal (SLR) application, the agency announced yesterday.

ASLBs conduct adjudicatory hearings on major licensing actions by the NRC. Their rulings may be appealed to the commission.

The SLR application, submitted by Dominion Energy last August, was docketed by the NRC in October. The petition objecting to it was filed in December by three antinuclear organizations—Beyond Nuclear, Sierra Club, and Alliance for Progressive Virginia.

On February 4, beginning at 2 p.m. Eastern time, the ASLB will address a rule waiver request from the groups, as well as the admissibility of their proposed contention. The board will entertain comments from representatives for the petitioners, Dominion, and NRC staff.

NRC accepts Point Beach SLR application

January 26, 2021, 7:01AMNuclear News

The Nuclear Regulatory Commission has accepted for review NextEra Energy’s subsequent license renewal (SLR) application for its Point Beach reactors, making them the fifth and sixth units currently under consideration for a second 20-year license renewal. (SLR applications for Dominion Energy’s North Anna-1 and -2 and Surry-1 and -2 are also being reviewed, while SLR approval has been granted for Exelon’s Peach Bottom and NextEra’s Turkey Point units.)

NextEra submitted the SLR application in November of last year—the first such application involving a Midwestern nuclear plant. The NRC approved the plant’s initial license renewal in December 2005, allowing Unit 1 to operate through October 5, 2030, and Unit 2 through March 8, 2033.

NRC likely to grant second license renewals

April 16, 2020, 2:14PMNuclear News

Surry Power Station. Photo: Dominion Energy.

The Nuclear Regulatory Commission issued its final supplemental environmental impact statement (EIS) on April 6 for Dominion Energy’s subsequent license renewal (SLR) application for Surry-1 and -2, concluding that the potential environmental impacts from continued operation of the units are not substantial enough to prevent the agency from considering issuance of the SLRs. The NRC had issued its final safety evaluation report on the Surry SLR application on March 9, with a similarly positive conclusion.