Salt Waste Processing Facility at SRS approved for start

August 18, 2020, 3:03PMRadwaste Solutions

The Department of Energy approved the start of operations at the Salt Waste Processing Facility (SWPF) at the Savannah River Site (SRS), authorizing hot (radioactive) operations to begin at the facility, the agency announced on August 17.

The approval comes five months ahead of the current baseline completion date of January 31, 2021. Parsons Corporation, which designed and built the first-of-a-kind facility, will operate it for one year.

“This is a considerable achievement for EM's (Environmental Management) cleanup program and will drive significant progress in treating the tank waste at SRS in the next decade,” said William “Ike” White, senior advisor for the EM to the Under Secretary for Science.