OPG completes Darlington refurbishment construction

February 3, 2026, 9:34AMNuclear News
The full-scale reactor mock-up at Darlington nuclear power plant helped train workers to execute the refurbishment project. (Photo: OPG)

Ontario Power Generation, Canada's leading power generator, has completed construction work on its massive Darlington refurbishment project, the utility announced yesterday. The overall project is forecast to be delivered four months ahead of schedule and C$150 million (about $110 million) under budget, OPG stated, adding that station staff are now completing final testing on the Unit 4 reactor in preparation of its return to full commercial operation.