The Nuclear Regulatory Commission has issued its final environmental impact statement on an application by Interim Storage Partners for a license to construct and operate a consolidated interim storage facility for spent nuclear fuel in Andrews County, Texas. After considering the environmental impacts of the proposed action, the NRC announced today that its staff has recommended granting the proposed license.

The project: Interim Storage Partners is a joint venture of Waste Control Specialists and Orano CIS, a subsidiary of Orano USA. If granted, the license would authorize ISP to construct a facility to store up to 5,000 metric tons of spent commercial nuclear fuel, as well as Greater-Than-Class C waste, for a period of 40 years. ISP plans to expand the facility to a total capacity of 40,000 metric tons of spent fuel. The facility would be built adjacent to Waste Control Specialists’ low-level radioactive waste disposal site.

Public comments: The NRC published a draft environmental impact statement on the project in May 2020. Agency staff held four public meetings by webinar to present the draft findings and receive public comments. The staff received and evaluated about 2,500 unique comments submitted by nearly 10,600 members of the public.

Final EIS: The NRC will provide the final environmental impact statement to the Environmental Protection Agency for filing.

Once the EPA publishes in the Federal Register a notice that it has received the document, the NRC must wait at least 30 days before issuing a licensing decision. When it announces its licensing decision, the NRC will also publish its final safety evaluation report detailing its technical review of the ISP application.

There’s more: Additional information about the NRC staff’s review of the ISP application is available on the NRC website.


Related Articles

Insights from the Three Mile Island accident—Part 2: Improvements

The accident at Three Mile Island revealed many areas for improvement in the safety of nuclear power that have been addressed continuously in the past 40 years.

May 6, 2022, 3:06PMNuclear NewsWilliam E. Burchill

Part one of this article, published in the May 2019 issue of Nuclear News[1] and last Friday on Nuclear Newswire, presented insights from the 1979 accident at Three Mile Island-­2 and...

Insights from the Three Mile Island accident—Part 1: The accident

Sparked by an article on the TMI accident that appeared in the March 2019 issue of Nuclear News, ANS past president William E. Burchill (2008–2009) offered his own views on the subject. Part 1 of the article appeared in the May 2019 issue of NN and Part 2 was published in June 2019.

April 29, 2022, 3:59PMNuclear NewsWilliam E. Burchill

The accident at Unit 2 of the Three Mile Island nuclear power plant on March 28, 1979, was an extremely complex event. It was produced by numerous preexisting plant conditions, many systemic...

NRC to consolidate LLW rulemaking

April 11, 2022, 9:30AMRadwaste Solutions

The Nuclear Regulatory Commission will integrate two separate rulemaking activities concerning the disposal of low-level radioactive waste, issuing a “re-proposed” rule that consolidates...