Demolition of former radioisotope lab underway at ORNL

February 24, 2021, 12:01PMRadwaste Solutions

A view of the demolition of a hot cell inside a protective cover at the former radioisotope development lab at ORNL. Photo: DOE

The Department of Energy’s Oak Ridge Office of Environmental Management and contractor UCOR have begun removing the two remaining structures at the former radioisotope development laboratory at Oak Ridge National Laboratory, in Tennessee.

“This project launches our next phase of major demolition and cleanup at ORNL,” said Nathan Felosi, ORNL’s portfolio federal project director for OREM. “Our work is eliminating contaminated structures, like this one, that are on DOE’s list of high-risk facilities and clearing space for future research missions.”

The project is scheduled to be completed this spring, OREM reported on February 23.

Hot cells: The structures being demolished are hot cells, heavily shielded concrete rooms that provided researchers protection from highly radioactive material during the years the radioisotope development lab was operational.

Constructed in the early 1940s, the lab contained six hot cells where radioisotopes from ORNL's graphite reactor and succeeding reactors were processed for shipment.

Four of the hot cells and an outer shell were demolished in prior years using funds from the American Recovery and Reinvestment Act of 2009.

Getting ready: UCOR completed several tasks to prepare the final structures for demolition. Workers eliminated contamination pathways, which involved pumping and grouting a 47-foot-long underground transfer tunnel that was used to load radioactive material into the hot cells.

UCOR also constructed a six-story protective cover over the hot cells to keep nearby research facilities protected during the demolition. Using a 175-ton crane, crews set a foundation of 92 blocks weighing 16,000 pounds each. Workers then used the crane to erect 20 steel trusses for the protected cover's frame. Nearly 12,000 square feet of fabric was added to the frame to complete the protective cover.

Waste transport: An intermodal rail system was built to transport boxes containing demolition debris to onsite storage. The system provides a safe way to transport the debris outside of the space-limited tented area, according to OREM.

“Removal of these hot cells is the first major demolition project associated with the environmental cleanup activities beginning to ramp up at ORNL,” said Susan Reid, UCOR project manager. “UCOR is proud to be part of this effort, working in collaboration with ORNL to remove unneeded facilities and facilitate the site’s expanding science missions.”


Related Articles

An open letter to Secretary Granholm

April 6, 2021, 9:09AMANS News

Madam Secretary: Congratulations on becoming America’s 16th secretary of energy! Welcome to one of the most misunderstood, confounding, yet important and underappreciated agencies in the...

Post-Fukushima safety enhancements

ANS flooding and seismic consensus standards assist the NRC and DOE in buttressing nuclear facility safety policies

April 2, 2021, 2:47PMNuclear NewsLeah Parks, Carl Mazzola, Jim Xu, and Brent Gutierrez

March 11 will mark the 10-­year anniversary of the Fukushima Daiichi event, when a 45-­foot tsunami, caused by the 9.0-­magnitude Great Tohoku Earthquake, significantly damaged the reactors...