Vogtle work slows, but start dates remain

May 6, 2020, 3:00PMNuclear News

The Vogtle-3 containment vessel in March. Photo: Georgia Power

Despite its recent decision to trim the workforce at the Vogtle reactor construction project by about 20 percent to better address the COVID-19 pandemic, Southern Company is confident that Units 3 and 4—twin AP 1000 pressurized water reactors—will be up and running according to schedule.

Pandemic prompts cuts to Vogtle construction workforce

April 23, 2020, 5:34PMNuclear News

As a result of the COVID-19 crisis, Georgia Power Company is reducing the number of workers at its Vogtle-3 and -4 construction site, in Waynesboro, Ga., by approximately 20 percent, according to a recent joint Securities and Exchange Commission filing by the company and parent firm Southern Company.

Virus impacts could slow Vogtle construction project

April 3, 2020, 10:30AMNuclear News

Ongoing efforts to deal with the coronavirus pandemic could hinder progress at the reactor construction project currently under way at the Vogtle nuclear plant near Waynesboro, Ga., according to a Southern Company report filed on April 1 with the Securities and Exchange Commission.