Saltstone Disposal Unit 11, center, has had all of its concrete work completed at the Savannah River Site’s Saltstone Disposal Facility in Aiken, S.C. (Photo: SRS)
The Savannah River Site has completed all concrete construction on its “mega-size” Saltstone Disposal Unit (SDU) 11 at the Saltstone Disposal Facility in Aiken, S.C. The several SDUs at the site are designed to provide safe, permanent storage for decontaminated salt solution from the Salt Waste Processing Facility (SWPF) as production is ramped up. The SDUs are crucial components of SRS’s liquid waste program, allowing the site to meet the cleanup responsibilities of the Department of Energy’s Office of Environmental Management.
All major concrete placements have been completed on Saltstone Disposal Unit 10, the latest megavolume disposal unit being built at the Savannah River Site. This aerial view shows the final roof section being installed on the unit. (Photo: DOE-EM)
With the placement of 25 wall sections, 208 support columns, and 7 roof sections, work crews have completed all major concrete placements for the megavolume Saltstone Disposal Unit (SDU) 10 at the Savannah River Site in South Carolina, according to the Department of Energy’s Office of Environmental Management.
The first wall section of Saltstone Disposal Unit 8 is being constructed at the Savannah River Site. Source: DOE
The first wall section of Saltstone Disposal Unit 8 (SDU 8) at the Department of Energy's Savannah River Site in South Carolina was installed earlier this month.
SDU 8 will stand 43 feet tall and 375 feet in diameter, and have a 33-million-gallon capacity, just like two SDUs built recently at the site. The 25 wall sections of SDU 8 are being constructed using high-strength, reinforced concrete and will be wrapped with seven layers of more than 300 miles of steel cable for added strength.
The flooring of SDU 8 is more than halfway complete. The concrete floor sits on top of a multilayer foundation: a geosynthetic clay liner and high-density plastic liner sandwiched between two concrete layers called “mud mats.” The floor is being completed in 14 sections.
The disposal units are built to safely and permanently contain decontaminated salt solution processed at Savannah River, the DOE reported on March 9.