A series of firsts delivers new Plant Vogtle units

January 17, 2025, 3:00PMNuclear NewsDot Schneider
The reactor building and the turbine building seen in October 2024 as employees worked on Vogtle Unit 3’s first-ever refueling outage. (Photo: Dot Schneider)

Southern Nuclear was first when no one wanted to be.

The nuclear subsidiary of the century-old utility Southern Company, based in Atlanta, Ga., joined a pack of nuclear companies in the early 2000s—during what was then dubbed a “nuclear renaissance”—bullish on plans for new large nuclear facilities and adding thousands of new carbon-free megawatts to the grid.

In 2008, Southern Nuclear applied for a combined construction and operating license (COL), positioning the company to receive the first such license from the U.S. Nuclear Regulatory Commission in 2012. Also in 2008, Southern became the first U.S. company to sign an engineering, procurement, and construction contract for a Generation III+ reactor. Southern chose Westinghouse’s AP1000 pressurized water reactor, which was certified by the NRC in December 2011.

Fast forward a dozen years—which saw dozens of setbacks and hundreds of successes—and Southern Nuclear and its stakeholders celebrated the completion of Vogtle Units 3 and 4: the first new commercial nuclear power construction project completed in the U.S. in more than 30 years.

To continue reading, log in or create a free account!

Related Articles

Nieh sworn in to NRC

December 9, 2025, 7:04AMNuclear News

The Nuclear Regulatory Commission is now back up to four commissioners. Following a 66–32 confirmation vote in the U.S. Senate last month, Ho Nieh was officially sworn in last week.He fills...

Deep Fission to break ground this week

December 8, 2025, 6:58AMNuclear News

With about seven months left in the race to bring DOE-authorized test reactors on line by July 4, 2026, via the Reactor Pilot Program, Deep Fission has announced that it will break ground on...