NN Asks: What hurdles stand in the way of nuclear power’s global expansion?

March 12, 2026, 7:49AMNuclear NewsJake Jurewicz

Jake Jurewicz

Nuclear technology is mature. It provides firm power at scale with minimal externalities and has done so for decades. The core problem isn’t about the technology—it is how the plants are built. Nuclear construction has a well-documented history of cost and schedule overruns. Previous nuclear plants often spent more than twice what was first budgeted, making nuclear among the power technologies with the largest average cost overruns worldwide.

Recent projects illustrate how severe the problem can be. In South Carolina, the V.C. Summer nuclear expansion saw projected costs rise from roughly $10 billion to more than $25 billion before the project was abandoned in 2017, by which time more than $9 billion had already been spent and customers were stuck paying for a site they have yet to benefit from.

In Europe, the U.K.’s Hinkley Point C offers a similar example. Approved in 2016 with an estimated cost of £18 billion (about $24.7 billion), the project’s expected cost has since risen reportedly to more than £40 billion (or more than about $54.8 billion). Such overruns cause the industry to turn to taxpayers and ratepayers to assume all of the risk, further disincentivizing cost and schedule reduction for the people carrying out the construction.

This creates a cycle that is hard to break out of and hurts the nuclear industry. When taxpayers are responsible for cost, public support does not improve, and delivery models do not innovate. Political pressure increases, injecting further uncertainty into project management, and each new project is seen as riskier than the last. Over time, these dynamics raise financing costs, slow down approvals, and constrain deployment.

Instead of designing nuclear sites as bespoke megaprojects that carry the risk of high cost overruns, nuclear projects should be designed to use fixed-price contracts enabled through standard form factors and off-site prefabrication and outfitting. Blue Energy is approaching this by designing plants to be built in existing fabrication yards using repeatable processes and proven supply chains. This approach enables fixed prices and removes risk from ratepayers and taxpayers.

The primary hurdle to nuclear power’s global expansion is the delivery and contracting model that weakens accountability and undermines trust. What’s encouraging is that this barrier is solvable. By borrowing proven methods from adjacent energy sectors like oil and gas, liquefied natural gas, and offshore wind, we can rebuild trust from capital markets and the public, and we can enable nuclear power to scale at the pace demanded by civilization’s growing needs.


Jake Jurewicz (jake@blueenergy.co) is the cofounder and CEO of Blue Energy.