Vogtle site makes progress with critical testing of new units

July 16, 2020, 3:15PMNuclear News

Closed vessel testing has been completed at Vogtle-3 at the Georgia Power site near Waynesboro, Ga., the company announced on July 14. The completion of the milestone prepares Unit 3 for cold hydro testing, which is required ahead of initial fuel load.

Vogtle-3 and -4 are the first new nuclear power reactors built in the United States in the past three decades. The new units will be powered by AP1000 reactors.

Georgia Power resequencing Vogtle-3 and -4 planned activities

June 24, 2020, 4:07PMNuclear News

From left: Vogtle-3 and -4. Photo: Georgia Power

Southern Company subsidiary Georgia Power, primary owner of the Vogtle nuclear power plant, announced on June 23 that it is resequencing certain planned activities at Vogtle-3 and -4, the two Westinghouse AP1000 units under construction at the site near Waynesboro, Ga.

Final major module for Vogtle-3 installed

May 27, 2020, 5:18PMNuclear News

The CB-20 module being installed at Vogtle-3. Photo: Georgia Power

A massive water tank has been placed atop the containment vessel and shield building roof at Vogtle-3, one of two AP1000 reactors currently under construction at Southern Company’s nuclear expansion project near Waynesboro, Ga. The installation represents the final module placement for the unit and marks the latest significant milestone to be reached at the Vogtle site.

Vogtle-3 integrated head package set in place

May 19, 2020, 10:36AMNuclear News

Vogtle-3’s integrated head package. Photo: Georgia Power

Southern Company subsidiary Georgia Power has placed the integrated head package (IHP) atop the Unit 3 reactor vessel at the Vogtle nuclear expansion project near Waynesboro, Ga., marking the latest major milestone in the construction of the first new U.S. nuclear reactors in more than 30 years.

Pandemic prompts cuts to Vogtle construction workforce

April 23, 2020, 5:34PMNuclear News

As a result of the COVID-19 crisis, Georgia Power Company is reducing the number of workers at its Vogtle-3 and -4 construction site, in Waynesboro, Ga., by approximately 20 percent, according to a recent joint Securities and Exchange Commission filing by the company and parent firm Southern Company.